Greenbriar Building Plan

An aerial view of Greenbriar shows the steel installation underway on the school's new classroom addition on the southeast side of the building.

An aerial view of Greenbriar shows the steel installation underway on the school's new classroom addition on the southeast side of the building. (October 29, 2026)

photo of steel installation

An aerial view of Greenbriar shows the steel installation underway on the school's new classroom addition on the southeast side of the building. (October 13, 2026)

Photo of student signing steel beam

Greenbriar students and staff had the chance to leave a permanent mark on their school—quite literally. As Build 28 construction projects continue across the district, each school invited students and staff to sign a 10-foot steel beam that will become part of their school's new construction. (October 6, 2026)

Photo of students, staff at groundbreaking with shovels and dirt

Greenbriar students, staff, district leaders, architects, and construction crews gather for a groundbreaking ceremony on May 15, 2026, to kick off construction. 

Photo of students in hard hats

Greenbriar students gather for a groundbreaking ceremony to kick off construction on May 15, 2026. 

Schematic design rendering of the new cafetorium (exterior).

Schematic design rendering of the new cafetorium (exterior).

Schematic design rendering of the new courtyard.

Schematic design rendering of the new courtyard.

Schematic design rendering of the new cafetorium.

Schematic design rendering of the new cafetorium.

Schematic design rendering of the new art and music hallway at Greenbriar.

Schematic design rendering of the new art and music hallway at Greenbriar.

A schematic design rendering of the new art room at Greenbriar. 

Schematic design rendering of the new art room at Greenbriar. 

Year Opened: 1949
Total Cost: $20.3MM

Major Projects 

  • Build a new classroom wing addition behind the gymnasium to replace the 75-year-old classroom wing along Greenbriar Lane
  • Build a cafetorium (cafeteria/auditorium) 
  • Renovate existing multipurpose room/cafeteria and adjacent classrooms 
  • Update fire alarm, sprinkler, and P.A. systems
  • Update playgrounds and improve accessibility

Projected Construction Timeline

  • Summer 2026: Greenbriar Phase I construction begins ✅
  • Spring 2027: Greenbriar Phase I construction completed (new classroom wing) 
  • Summer 2027: Greenbriar Phase II begins (cafetorium, multipurpose room renovation) 
  • Spring 2028: Greenbriar Phase II completed 

Each construction area will be enclosed and separated from students, staff, and daily school activities during the construction projects.