Greenbriar Building Plan
Year Opened: 1949
Total Cost: $20.3MM
Major Projects
- Build a new classroom wing addition behind the gymnasium to replace the 75-year-old classroom wing along Greenbriar Lane
- Build a cafetorium (cafeteria/auditorium)
- Renovate existing multipurpose room/cafeteria and adjacent classrooms
- Update fire alarm, sprinkler, and P.A. systems
- Update playgrounds and improve accessibility
Projected Construction Timeline
- April 2026 - June 2026: Greenbriar construction begins
- Feb. 2027 - April 2027: Greenbriar Phase 1 construction completed
- February 2028: Greenbriar Phase 2 completed
Each construction area will be enclosed and separated from students, staff, and daily school activities during the construction projects.